Project Description
Modification of load dispatch center to integrate a 90/33KV substation and PV power plant.
Scope includes supervision of SCADA system configuration, substation automation system commissioning, and installation of communication systems including SDH, MUX, teleprotection, weather stations, and UPS systems.
Following Process
System Integration
01
Integration of PV plant and substation systems
SCADA Configuration
02
Setup of automation and monitoring systems
Communication Systems
01
Installation of SDH, MUX, and teleprotection
Testing & Commissioning
04
End-to-end testing and system validation
Finalize the Project
Successful integration of PV plant with national control systems ensuring reliable monitoring and operation.