Company
ASEA Engineering
Category
Suez 500KV AIS Substation Retrofit
Start time
2023
Delivery
2023
Feedback
Operational for 2+ Years

Project Description

Retrofit of 500KV AIS substation circuit breakers including design, engineering, manufacturing, supply, installation, testing, and commissioning.

Scope includes replacement of 15 operating rods for 500KV circuit breakers to upgrade existing systems and enhance performance.

Following Process

Engineering Design

01

Technical assessment and retrofit planning

 

Manufacturing & Supply

02

Production of new operating components

Installation

01

On-site retrofit and system upgrade

Testing & Commissioning

04

System validation and successful operation

Finalize the Project

Successful retrofit of 500KV substation with stable operation over extended period.